On three continents

Distributed project management

The company Burckhardt Compression, specialized in the production of piston compressors, gave EPS the order to realize the project management tool ProMa for the electrical department. The following areas of application were in the focus: recording and processing of projects, creation of the project-specific instrument list, maintenance of master data.

auf-drei-kontinenten

We were allowed to support the company Burckhardt Compression in the following points:

  • Complete product development from design, realization and installation to further development and maintenance
  • All tasks of software engineering
  • Selection of the software component
  • Use of EPS infrastructure for project management
auf-drei-kontinenten
  • Development of a project management tool (ProMa)
  • ProMa must guarantee quality
  • ProMa must be available offline
  • ProMa must increase efficiency
  • National languages must be adjustable
  • Historization of the master data
  • Administration of employees, customers, suppliers, specification catalogues, project and instrument documents
  • Extensive search option
  • Standardization
  • Possibility to overwrite the input parameters for a high flexibility in the projects
auf-drei-kontinenten

During the implementation, the latest implementation of the product was demonstrated to the customer on a monthly basis and discussed in detail. In this way, maximum feedback on the product could be obtained with a minimum of effort on the part of the customer. According to the rule, attack the biggest risks first, the most difficult and important functions of the product were started. Thus, the first step was to start with the instrument list with all the complexity of the historization of the data sets. Also at this point the linking and interconnection of different data was at its highest.

Furthermore, the presentation and the operation adapted to the customer’s needs were connected with a lot of effort. Excel was chosen for the interactive interface between the plant CAD and the ProMa. This allows any corrections and adjustments to be made before importing into the ProMa. Excel was also chosen for the reporting. ProMa set up specific views in the database, which provide the necessary data for Excel.

The infrastructure tools Subversion and Gemini, operated by EPS, were used for project management. The issue tracking tool Gemini was also accessible to Burckhardt Compression employees without restrictions. In this way, data and documents could be managed and maintained without redundancy problems, as often happens via e-mail. Both the domain and the database model were defined via UML and generated from Enterprise Architect.

auf-drei-kontinenten
  • C#
  • .Net
  • WPF
  • NHibernate
  • Oracle
  • SQLite
  • UML: Enterprise Architect
  • Subversion
  • Issue Tracking: Gemini
auf-drei-kontinenten

Similar Projects

Get a quote

tranSvias Team
Yeesss - wir haben es geschafft!!!

tranSvias LSVA ist offiziell NETS-zertifiziert!

Herzlichen Dank unseren Pilotkunden für ihre Geduld, das ehrliche Feedback und Vertrauen!